city streetcar

Jay Hanselman

Crews officially began demolition work Monday on two vacant buildings at the corner of Race and Henry in Over-the-Rhine.  The site is being cleared to construct the new maintenance facility for the streetcar system.  

It's where the vehicles will be cleaned and maintained and operations staff will be housed.  

Project Manager John Deatrick said this is a visible sign of construction since most streetcar work has been underground moving or repairing utilities.  He said that task will also continue.

Jay Hanselman

Cincinnati's City manager said Friday the city is close to awarding a contract to build the streetcar project.

Milton Dohoney, Jr. said in a memo the streetcar project has sufficient funding to allow it to proceed.

He said city administrators are in the final stages of discussions with a partnership involving Cincinnati-based Messer Construction and Prus/Delta Railroad JV.

City of Cincinnati

Some preliminary construction work on the Cincinnati streetcar project will result in a downtown street closing this weekend.

Duke Energy will be working at the intersection of Fifth and Walnut Streets to relocate underground electric facilities, according to a press release from the city.

The closures will begin Friday at 6 p.m. and remain in place until Monday at 6 a.m.

West Fifth Street will be closed between Vine and Main.  Walnut Street will be closed between East Sixth and East Fourth.

City of Cincinnati

Cincinnati Council is ready to give city administrators an additional $17.4 million to build the first phase of the much debated streetcar project.  

The Budget and Finance Committee approved the extra money Monday with a 5-4 vote.  The full Council will consider it Wednesday.  

The additional funds are coming from a variety of sources including other capital accounts and more bonding.  

Council Member Yvette Simpson remains supportive of the streetcar.

City of Cincinnati

Cincinnati City Manager Milton Dohoney spent more than two-and-a-half hours Monday answering questions about his plan to find an additional $17.5 million to build the streetcar project.  

About two weeks ago he suggested using funds from several different sources to cover the gap.  

Dohoney was asked about future cost overruns with the plan?  He said that’s possible, but there is some certainty.